Have you ever wondered when Massachusetts’ 6-year statute of repose for defective design, planning and construction is triggered when dealing with the construction of a multi-building, multi-year condominium construction project?
If you haven’t thought about such an issue that’s okay, neither had the United States District Court for the District of Massachusetts, nor the Supreme Judicial Court of Massachusetts. However, luckily for us, the Supreme Judicial Court recently tackled this very question in D’Allessandro v. Lennar Hingham Holdings, LLC, 156 N.E.3d 197, 198 (Mass. 2020).

In D’Allessandro, the Hewitts Landing Condominium project (the “Project”) consisted of 150 condominium units and twenty-eight buildings. D’Allessandro, 156 N.E.3d at 199. The Project was built over the course of twenty four different phases between 2008 and 2015; however, as individual units were